GIS Request Management - Planned Effort

731
4
Jump to solution
10-02-2024 08:18 AM
CodySteggell
Emerging Contributor

I've been setting up the GIS Request Management solution for our team, and it’s working really well for our needs. However, I’m encountering an issue with the effort bar graph on the activities dashboard. Whenever actual effort hours are added on the update page, the bar chart seems to compound the planned effort hours each time it’s submitted. I believe this happens because the original planned effort is being re-entered and summed in the dashboard.

Could I be using it incorrectly? Should the planned effort be removed when adding actual effort hours? Is there a way to keep the original planned effort displayed without it being added again if nothing else changes? Without clear understanding or training, staff may just add effort hours and leave everything else unchanged.

1 Solution

Accepted Solutions
BrandiRank22
Esri Contributor
4 Replies
BrandiRank22
Esri Contributor

@CodySteggell  are you deploying in AGOL or Enterprise?

0 Kudos
CodySteggell
Emerging Contributor

Enterprise

0 Kudos
BrandiRank22
Esri Contributor

@CodySteggell  - Please see the latest blog post - https://community.esri.com/t5/arcgis-solutions-blog/gis-request-management-error-in-gis-activities/b...

This issue wasn't identified until after release.

CodySteggell
Emerging Contributor

Thank you so much. 