Hello All,
Sorry if this is long but I am having a hard time getting answers through Tech demos from the Esri crew and need to know a bit more before I try to convince my employers to switch over to Survey 123.
for a summary of what we do: We inspect construction sites once a week (300ish sites between all inspectors) and send out pdfs to clients with the summaries and actionable items. There are just a few things I'm not sure whether or not they are possible with survey 123.
First- We need to have semi-dynamic surveys and would prefer to not have to create new surveys for each site. By dynamic I mean that some sites will have 3 photos of a location, specifying 1-3 BMPs that we inspected, while another site might have only 1, or maybe 12. I think we could manage this through repeats but I'm not sure. It would be nice to have these split up by zone (i.e. north boundary, midsite, south boundary, etc...) so I think maybe a repeat for each zone allowing each site to have variable listings within those zones? Can photos be used in repeats?
Second- It would be preferred to be able to use or copy over the previous weeks report and just replace some photos and change comments on the next weeks inspections. Therefore if we wrote a long description of an item and it is unchanged, we can leave the comment and replace the photo. Not sure if this is possible or not.
Third- Would it be possible to take the date from one report submission, and populating it into a "previous inspection date" field on the next report?
Finally- we would like to attach a markup of a design to one of the last pages, are you able to include that in the report generating process, or would we simply have to insert that page to the generated PDF?