Frequent Contributor

In the gaps table, anyone know what the Gap_Type codes mean? I have values 0, 1 and 2.

Thanks.

0 Kudos
1 Solution

Accepted Solutions
PhilipHardy
Emerging Contributor

Ryan, this field specifies if the gap is a measure gap = 0, a physical gap = 1, or both = 2.  A measure gap is where there is a difference in the M value from one side of the gap to another. A physical gap is when there is an XY difference from one side of the gap to another.

View solution in original post

4 Replies
ColinSchut
Occasional Contributor

This is a guess, but could it be Gap Calibration type (Stepping increment, adding increment or adding euclidean distance)? We only have stepping increment gaps and all my types are 2.

RyanKoschatzky
Frequent Contributor

I thought that also however we have only used euclidean distance so I wouldn't think we would have the other two types. 

0 Kudos
PhilipHardy
Emerging Contributor

Ryan, this field specifies if the gap is a measure gap = 0, a physical gap = 1, or both = 2.  A measure gap is where there is a difference in the M value from one side of the gap to another. A physical gap is when there is an XY difference from one side of the gap to another.

RyanKoschatzky
Frequent Contributor

Thanks Phil.