Hello everybody,
Resolved: Called ESRI Support, we found that having 2 constants gave the equation a 0 and I had to multiply the constants together. Is there a way around this?
29.84*.90*pow(${Outlet_Size}, 2)*sqrt(${Pitot_Pressure})
turned into
26.856*pow(${Outlet_Size}, 2)*sqrt(${Pitot_Pressure})
Hi Adam,
Can you please share a copy of the xlsx file so we can take a closer look? It is much easier to troubleshoot with the xlsx file to see all the settings and configuration for all questions, compared to just looking at the screenshots.
Phil.
Hi Philip, I updated my original post info. Don't have access to file right now but will soon, and can post. Thanks