I am working on delineating watersheds in a very flat spring driven system. NHD data only describes two of the major streams in the watershed, so I had to digitize the stream courses and use them as the Flowlines inthe analysis. I am able to build the catchments not problem but when I try to create the adjointcatchments something is amiss. Only two headwater streams are considered adjoint. This is not correct as several headwater sections should be included as parts of larger dowstream watersheds. Has anyone ran into this problem before? One other point is that I have had to manually update the HydroIDs throughout the process as ArcHydro is writing Hydro IDs as if the watershed outlet was a headwater stream - aka everything is backwards. Thanks in advance for any help you can offer.
Sincerely,
Tim