Hi all,
I have a question on appending events (in my case changing the to date of an already registered event) with a date range that temporally overlaps with one or more route realignments
Event: From Date: 2010/01/01 To Date: NULL
Route realignment occurred 2015/01/01 for instance.
Appending the event or changing the TODATE to overlap with that realignment will correctly date split the event. But the measures are not updated to the new network locations causing the event to spatially move.
In my case I can locate the updated events to their previous location and update the measure fields manually, but this would be impossible on a more complicated network. The only other thing I can think of is prepping the data to have a full set of event records for every route date range and locating them all. Is there a workflow that will simplify this?