First question: when I want to use the Overpelt Fabriek site as the start and end depot, is it enough to just load it as a location for the Depots? You can see in attachment the example for route 1 for which I loaded 378 locations as the orders and the Overpelt Fabriek site as the Depot.
Second question: How can I add the number of orders in the area as the MaxOrderCount for each route?
Thanks again Anna!However, still 2 questions.First question: when I want to use the Overpelt Fabriek site as the start and end depot, is it enough to just load it as a location for the Depots? You can see in attachment the example for route 1 for which I loaded 378 locations as the orders and the Overpelt Fabriek site as the Depot.Second question: How can I add the number of orders in the area as the MaxOrderCount for each route?Many thanks again! Problem is almost solved 🙂Thomas
Hi Thomas,Your problem is simpler than I thought. For each area, you only need one route. You can use Overpelt Fabriek site as the start and end depot, and use the number of orders in the area as the MaxOrderCount for the route.Since the all orders in an area will be assigned to one route, solving the problem will take a while.Thanks.anna
1) After the first dot is visited, the next dot to be visited is the dot that is the closest to the first dot. The third dot, is the dot that is the clost to the second dot, and so on. In general, one could say that the next dot is the dot closest to the current dot, except dots that are already visited.
Membros conectados podem postar, seguir atualizações e mais. Novo aqui? Registre uma conta gratuita.
Find useful guides, FAQs, and documents to help you navigate and make the most of Esri Community.