UPDMの同じデータでは、駅に単一の規制装置がありますが、実際には特定の路線に沿って異なる「operator」と「monitor」規制装置が存在する場合はどうでしょうか? これら両方の機器をモデル内のデバイスとして表現することに利点はありますか?
ご意見を事前にありがとうございます、
Ed
Hi Ed,
My opinion is that there are two answers to your question.
Answer 1. There is no benefit to the capabilities of the Utility Network to mapping both regulators. The defining the pressure zone only requires 1 of the regulators. The operator regulator is the pressure controlling regulator and should be designated as the subnetwork controller for the pressure zone.
Answer 2. From an engineering perspective, mapping both the operator and monitor regulators provides a more accurate representation of the installed components at the regulator station. It may also be of value to the hydraulic modeling.
Tom DeWitte
Makes sense. Thanks for the feedback.