I am trying to use my centimeter-grade Trimble R2 with ESRI Collector on my Ipad to shoot XY and Z coordinates for civil engineering projects.
I have shot several USGS benchmarks with this equipment and I consistently get a Z value that is between 0.62 and 0.35 feet below the established elevations for these benchmarks.
I also collected hundreds of project-related points with this equipment including a professional-surveyor-established TBM. When I run a bench circuit with my traditional rod and level, shooting the NAD 83 NAVD 88 TBM and many hard-surface points I average 0.47 feet above the same points shot with the R2.
In both of these scenarios the R2 values are consistently approximately half a foot below the values that I determine to be “correct”. Usually 0.45 to 0.55 feet.
I am hoping (as I always do) that someone can point out a simple mistake that I am making and a simple solution to correct this.