Hi,
I came across this error when trying to apply an Asset Package to an Enterprise Utility Network Geodatabase"
Error: Junction Pillar - Valid Paths are only valid for 3 or 4 terminal configurations error
We have defined Junction Pillar features with 8 terminals in the data model. In the Asset Package B_tables, we have the 8 Junction Pillar terminals defined in the the B_TerminalConfiguration_Terminals table and valid paths defined in the B_TerminalConfiguartion_ValidPath table, as per below:


By removing the Junction Pillar entry out of the B_TerminalConfiguartion_ValidPath table, I was able to successfully apply the Asset Package to the Utility Network.
Question:
Why Valid Paths are only valid for 3 or 4 terminal configurations? (and not also for terminal configurations greater then 4?)
Thanks
Damien Pyne - FYI