Hello!
I have a geodatabase sync process that 1) synchronizes distributed geodatabase changes from a production geodatabase to a staging geodatabase, 2) where I do some stuff, and then 3) synchronize from the staging geodatabase to a publication database--three steps.
Step 3) to publication is time sensitive, and if there are a bunch of incoming changes from steps 1) and 2) I will need to plan for a little downtime. Does anyone know how to get a count of features that were transferred during geodatabase synchronization so that I can get an estimate of how long step 3 will take?
Thanks!