Is there a way to cancel an Analysis that is taking too long?

1749
2
10-27-2015 09:36 AM
RyanBrubaker1
New Contributor

I started a watershed analysis using some DEM points. The layer is visible in the map and has been churning for over an hour. Is there a way to tell how long it will take or even cancel the analysis?

Tags (2)
0 Kudos
2 Replies
DanPatterson_Retired
MVP Emeritus

was this using a tool in arcmap? and it doesn't have a cancel button? or it doesn't respond?

0 Kudos
RyanBrubaker1
New Contributor

This was on ArcGIS Online... I eventually removed the layer that it was creating for the watersheds in My Content and after a few minutes it got rid of the processing in my map. But I didn't see an obvious way to cancel or see what the progress was on the Analysis. It also appeared that I could not Save my map while it was running.