Network Analyst: Failure while working with internal OD Cost matrix, Out of Memory

1941
0
04-26-2010 07:52 AM
PawanVuppala
Occasional Contributor
Hi,
I am fairly new to using Network Analyst. I have a request to create VRP solve for two field inspectors going out to inspect 5700 properties.  When I add orders, Depots and Routes and hit solve I get this error saying "Failure while working with internal OD Cost Matrix" and Error" Out of Memory", I was able to solve it for like 50 orders and running it for more points but I really would like to get a full solve on all records.  Is it possible or do I have to split the visits ?  Is there a limit on how many orders or destinations can VRP solve?
http://resources.arcgis.com/content/kbase?fa=articleShow&d=30637
I looked at this forum and I hope this will fix the issue but, please let me know if you guys have any ideas..
Im using 9.3 SP1

I Appreciate everyone for helping with thoughts on this.

-Pawan
Tags (2)
0 Kudos
0 Replies